Behavior of the Options

This section describes the behavior of Integration Wizard Preferences option and its corresponding option on the process wizard page.

Allow Loading Forecast in the Current Status Period

Integration Wizard Preferences Tab Option Resource Assignments Page of the Integration Wizard Option
Selected Secure New Configuration Existing Configuration
Yes No Yes ¦ Enabled Follows the selection in the configuration file
Yes Yes Yes ¦ Disabled Follows the selection on Integration Wizard Preferences tab
No No No ¦ Enabled Follows the selection on Integration Wizard Preferences tab
No Yes No ¦ Disabled Follows the selection in the configuration file

Delete Milestones No Longer in the Schedule

Integration Wizard Preferences Tab Option Change Control Page of the Integration Wizard Option
Selected Secure New Configuration Existing Configuration
Yes No Yes ¦ Enabled Follows the selection in the configuration file
Yes Yes Yes ¦ Disabled Follows the selection on Integration Wizard Preferences tab
No No No ¦ Enabled Follows the selection on Integration Wizard Preferences tab
No Yes No ¦ Disabled Follows the selection in the configuration file

Notes

  • Yes indicates that the checkbox is selected.
  • No indicates that the checkbox is cleared.
  • Enabled means you can still select or clear the checkbox.
  • Disabled means you can no longer select or clear the checkbox.